Cycle time, throughput, a cumulative flow diagram and a Monte Carlo delivery forecast β all derived from the stage-transition history your Priority Board already records. Load a board and the numbers are there; nothing needs re-entering, and nothing is uploaded.
Flow Metrics turns the stage-transition history recorded by the Convsta Priority Board into the views flow-based teams rely on: a cycle time scatterplot with 50th, 85th and 95th percentile lines, weekly throughput, a cumulative flow diagram, the median and 85th-percentile time items spend in each stage, and a Monte Carlo delivery forecast. It finds a board saved in this browser (localStorage, sessionStorage, IndexedDB or Cache Storage), or takes an imported or pasted JSON export. It only reads β there are no network calls and nothing is written back to your board.
Cycle time and throughput answer different questions. Cycle time is per item: the time from the commitment point β the stage chosen under "Clock starts when work reaches", by default the one after the intake queue β until the item first lands in a stage marked as done. Lead time, measured from creation instead, is included in the CSV export. Throughput is a rate: items finished per day, with empty days kept as zeros because a day with no deliveries is data too. The two are tied together by work in progress through Little's Law (average cycle time β WIP Γ· average throughput), which is why capping WIP is usually the quickest way to shorten cycle time. Percentiles are reported instead of averages because cycle time distributions are right-skewed: a handful of stalled items drags the mean well away from what a typical item experiences. The 85th percentile reads as "85% of items finished within this long" and makes a sensible service-level expectation.
It runs 10,000 simulations. Each one repeatedly draws a random day, with replacement, from your real daily throughput over the sampled weeks and adds up the completions until the item count is reached; the number of days that took is recorded. The histogram is the spread of those outcomes. The 50% line is a coin flip, 85% is a reasonable planning date, and 95% is the one to commit to externally. The item count defaults to your current work in progress.
Resampling assumes the near future looks like the sample period. If that period included a holiday shutdown, a team change, or a batch of items closed in one clean-up, choose a different number of weeks. It also assumes the remaining items are similar in size to the ones already finished.
The board needs a stage flagged as done, items finished inside the chosen window, and finished items that passed through the commitment stage. The notice names whichever ingredient is missing, so you can widen the window or move the commitment point.
The chart uses a five-step colour ramp, so a pipeline with more than five stages is folded into five bands of adjacent stages; the table view still lists every stage separately. The diagram covers at most the last 120 days.